ABBEY DAWN KINGSTON – (600 kW BUILT)

As a first time Ontario experience, this project allowed us to test the limits on working with difficult terrain, wet and muddy sites. This installation was able to take place during one of the wettest months on record in Ontario. The above ground ballast allowed the developer the flexibility to use this site that otherwise would have been unfeasible.

Monitor this system in real time here.

abbey-thumb


Plant location: 
Kingston, Ontario, Canada

EPC: UGEI – Endura

kW DC:600

kW AC:500

Commissioning Date: March 2017